Detailed Study Notes for Unit III
Detailed Study Notes for Unit III
Unit-III: Discharge of Contracts and Breach
1. Concept of Discharge of Contracts
A. Meaning of Discharge
- Definition: Discharge of a contract means the termination of the contractual relationship and obligations between the parties. Once a contract is discharged, the parties are absolved from any further performance under it.
B. Modes of Discharge
A contract can be discharged through several recognized modes:
- Performance of contract.
- Mutual consent or agreement (Novation, Rescission, Alteration, Remission).
- Impossibility of performance (Doctrine of Frustration).
- Operation of law (Insolvency, merger, death in personal skill contracts).
- Breach of contract (Actual or Anticipatory breach).
2. Discharge by Performance
A. Performance by Parties (Section 37)
- Parties to a contract must either perform, or offer to perform, their respective promises, unless such performance is dispensed with or excused under the provisions of the Act.
- Actual Performance: When both parties fully perform their obligations within the stipulated time.
- Attempted Performance (Tender): When the promisor offers to perform their obligation, but the promisee refuses to accept it. The promisor is not responsible for non-performance and does not lose their rights under the contract.
B. Appropriation of Payments (Sections 59 to 61)
When a debtor owes multiple distinct debts to the same creditor and makes a payment that is insufficient to discharge all debts, the rules of appropriation apply:
- Debtor’s Express Instruction (Section 59): Where the debtor expressly states at the time of payment which debt the payment is to be applied to, the creditor must apply it accordingly.
- Creditor’s Discretion (Section 60): If the debtor gives no express or implied indication, the creditor may apply it at their discretion to any lawful debt actually due and payable (including a time-barred debt).
- Order of Time (Section 61): If neither party makes any appropriation, the payment must be applied in discharge of the debts in order of time (chronological order).
C. Performance by Joint Promisors (Sections 42 to 45)
- When two or more persons have made a joint promise, all joint promisors must fulfill the promise jointly during their lives, and after death, their legal representatives jointly.
- Release of One Joint Promisor (Section 44): The release of one joint promisor by the promisee does not discharge the other joint promisor(s), nor does it free the released promisor from responsibility to the other promisors.
3. Discharge by Mutual Agreement or Consent (Sections 62 & 63)
A. Modes of Discharge by Agreement (Section 62)
If the parties to a contract agree to substitute a new contract for it, or to rescind or alter it, the original contract need not be performed:
- Novation: Substitution of a new contract in place of the original one (either between the same parties or involving a new party). The original contract is discharged and need not be performed.
- Rescission: Cancellation of the contract by mutual consent of the parties.
- Alteration: Modification of one or more terms of the original contract with mutual consent.
B. Remission and Accord & Satisfaction (Section 63)
- Remission: Every promisee may dispense with or remit, wholly or in part, the performance of the promise made to them, or may extend the time for such performance, or accept any satisfaction instead of it.
- Accord and Satisfaction: “Accord” is the agreement to accept some alternative performance in satisfaction of the original claim; “Satisfaction” is the actual execution or performance of that agreement, which discharges the original contract.
4. Discharge by Impossibility of Performance (Doctrine of Frustration – Section 56)
A. Initial vs. Subsequent Impossibility
- Initial Impossibility (Void ab initio): An agreement to do an impossible act in itself is void (Paragraph 1 of Section 56).
- Subsequent Impossibility (Doctrine of Frustration): A contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful (Paragraph 2 of Section 56).
B. Grounds / Instances of Frustration
- Destruction of Subject Matter: If the specific subject matter essential for performance is destroyed without fault of either party (Taylor v. Caldwell).
- Death or Incapacity of Parties: In contracts involving personal skill or services.
- Change of Law: When a subsequent change in law makes performance illegal.
- Declaration of War: Makes trading with an alien enemy illegal.
- Non-occurrence of a Particular State of Things: Where the foundational basis of the contract collapses (Krell v. Henry).
C. Exceptions where Frustration Does NOT Apply
- Commercial hardship or mere financial unprofitability.
- Self-induced frustration (where impossibility is caused by the negligence or default of one party).
- Strikes, lockouts, or commercial civil disturbances that are foreseeable or provided for in the contract.
5. Discharge by Breach of Contract
A. Anticipatory Breach
- Definition (Section 39): When a party to a contract has refused to perform, or disabled themselves from performing, their promise in its entirety, the promisee may put an end to the contract, unless they have signified, by words or conduct, their acquiescence in its continuance.
- Options for the Promisee:
- Rescind the contract immediately and sue for damages for breach before the actual date of performance.
- Treat the contract as subsisting, wait for the due date of performance, and hold the other party liable for actual breach.
B. Actual Breach
- Occurs when a party fails or refuses to perform their obligations under the contract on the exact due date of performance, or performs defectively during performance. The injured party is immediately discharged from their obligations and entitled to sue for remedies.
6. In-Depth Landmark Case Studies
Case Study 1: Doctrine of Frustration and Destruction of Subject Matter
- Case Title: Taylor v. Caldwell
- Citation & Court: [1863] EWHC QB J1 (Court of Queen’s Bench)
- Related Statutory Sections: Section 56 of the Indian Contract Act (Agreement to do impossible act / Subsequent impossibility).
- The Story & Real-Life Background: The plaintiffs agreed to rent the Surrey Gardens and Music Hall from the defendants for four specific concert dates to host musical performances. Before the first concert date, the music hall accidentally caught fire and burned to the ground completely, without any fault of either party. The plaintiffs sued the defendants for breach of contract to recover advertising and preparation expenses.
- Legal Issues Involved: Whether the accidental destruction of the subject matter of a contract discharges both parties from performance under the doctrine of implied term/impossibility.
- Final Judgement & Ratio Decidendi:
- Ruling: The court held that the contract was subject to an implied condition that the parties shall be excused if performance becomes impossible due to the destruction of the underlying subject matter without fault. Consequently, both parties were discharged from their obligations.
- Ratio: When an event occurs rendering performance physically impossible through no fault of the parties, the contract is frustrated and discharged.
Case Study 2: Anticipatory Breach and Immediate Right to Sue
- Case Title: Hochster v. De La Tour
- Citation & Court: [1853] EWHC QB J18 (Court of Queen’s Bench)
- Related Statutory Sections: Section 39 of the Indian Contract Act (Effect of refusal of party to perform promise wholly).
- The Story & Real-Life Background: In April 1852, the defendant engaged the plaintiff to act as a courier on a foreign tour starting on June 1st. On May 11th, the defendant wrote to the plaintiff stating he had changed his mind and no longer required his services. On May 22nd, before the scheduled June 1st starting date, the plaintiff filed a lawsuit for breach of contract. The defendant argued the suit was premature since the performance date had not yet arrived.
- Legal Issues Involved: Whether an injured party can sue for breach of contract immediately upon receiving an anticipatory repudiation, or whether they must wait until the actual date of performance.
- Final Judgement & Ratio Decidendi:
- Ruling: The court held that the plaintiff was entitled to treat the renunciation as an immediate breach and sue at once without waiting for June 1st. Waiting until the performance date would force the plaintiff to remain idle and unable to mitigate damages by taking alternative employment.
- Ratio: An anticipatory breach gives the innocent party an immediate right to elect to terminate the contract and sue for damages right away.
Quick Reference Guide: Unit-III Contract Act
| Unit Number | Act / Subject Name | Relevant Sections Range | Core Description / Subject Matter |
| Unit-III | Indian Contract Act, 1872 | Sections 37 to 67 | Discharge by performance, appropriation, joint promisors, novation, impossibility (frustration), and breach. |